Largo's Brazilian mine on schedule despite setbacks

Jun 17, 2013 | 06:36 PM | Daniel Fitzgerald

Tags  Largo Resources, vanadium mining, ferrovanadium production, Maracas project, Andrew Hancharyk, Daniel Fitzgerald

NEW YORK — Largo Resources Ltd. said its Maracás vanadium project in Brazil is on schedule for commissioning at the end of 2013 despite delays in the delivery of some equipment.

Mechanical erection of the electrical switchyard and main substation is complete and pre-commissioning has recently been concluded, the company said. Final commissioning of these areas will occur after completion of the 86-kilometer (53.4-mile) power line, which is half finished.....