Rain impacts Windimurra FeV output, sales

Jan 31, 2014 | 05:00 PM | Daniel Fitzgerald

Tags  ferrovanadium, Atlantic Ltd., reduced output, delayed maintenance, Windimurra facility, Australia, rain event, extended shutdown ferrovanadium shipments

NEW YORK — Atlantic Ltd.’s ferrovanadium production has been impacted by delayed maintenance at its Windimurra facility in Australia, which experienced a "major rain event" in late January, the company said in its latest quarterly production report.

Windimurra produced 298 tonnes of contained vanadium in the fourth quarter of 2013, up from 92 tonnes in the preceding quarter, as the facility continued its ramp-up in the second half of 2013. ....